1320kw Cat Diesel Generator - pad mounted on grade

anyone have a good guesstimate of man hours to build out and wire unit itself?

this is to be a permanent backup...wiring will already be inside the generator (feed to ATS is already considered)...

I'm anticipating about 70-80 man hours to attach all the parts, tie in feed, ground, etc...

anyone have any thoughts?
 
1320kw Cat Diesel Generator - pad mounted on grade

anyone have a good guesstimate of man hours to build out and wire unit itself?

this is to be a permanent backup...wiring will already be inside the generator (feed to ATS is already considered)...

I'm anticipating about 70-80 man hours to attach all the parts, tie in feed, ground, etc...

anyone have any thoughts?