jmellc
Senior Member
- Location
- Durham, NC
- Occupation
- Facility Maintenance Tech. Licensed Electrician
I recently helped a few days on a coworker's job.
This was a fairly small job that should have been relatively quick & easy but not so at all.
There were a few small physical challenges with methods of routing cables and having to move things in another tenant's basement below to run conduit there. But the main challenge was the customer, a GC. Their main project manager was OK but several partners over his head were constantly making changes. They also got hung up on the cost of fire rated floor boxes & kept pushing us to get new quotes. All quotes were within about $200 of each other, for 3 kits. A set of prints only showed up for the first inspection. Until then, the PM worked from a laptop drawing and we had to go to him to look at it, if he wasn't doing something else. We started off with 2 wall mounted TV's, and wound up with 7. 2 treadmills were wanted, but the rooms for them kept changing. A beer keg cooler was part of it too, a foolish item for an office IMHO. On top of it all, the main partner kept complaining we were not finished yet, even as he was making further changes.
I understand a wishy washy customer when it is a flaky college professor or a housewife who doesn't do these things very often. I do not understand such BS from a general contractor. A GC should know better than anyone the value of making a plan and sticking to it.
I don't yet know how it came out but I think we should have told them at the start to call us back when they decided what they wanted. This was a foolish way to do a job and they should have known better.
This was a fairly small job that should have been relatively quick & easy but not so at all.
There were a few small physical challenges with methods of routing cables and having to move things in another tenant's basement below to run conduit there. But the main challenge was the customer, a GC. Their main project manager was OK but several partners over his head were constantly making changes. They also got hung up on the cost of fire rated floor boxes & kept pushing us to get new quotes. All quotes were within about $200 of each other, for 3 kits. A set of prints only showed up for the first inspection. Until then, the PM worked from a laptop drawing and we had to go to him to look at it, if he wasn't doing something else. We started off with 2 wall mounted TV's, and wound up with 7. 2 treadmills were wanted, but the rooms for them kept changing. A beer keg cooler was part of it too, a foolish item for an office IMHO. On top of it all, the main partner kept complaining we were not finished yet, even as he was making further changes.
I understand a wishy washy customer when it is a flaky college professor or a housewife who doesn't do these things very often. I do not understand such BS from a general contractor. A GC should know better than anyone the value of making a plan and sticking to it.
I don't yet know how it came out but I think we should have told them at the start to call us back when they decided what they wanted. This was a foolish way to do a job and they should have known better.