Just gettn opinions. There is a duplex that was once fed by 1 meter that then fed 2 main service breakers that fed each panel from each. The local inspector wants two service disconnects now. How would u bring this up to code? there also is no ground to the panel or for the disconnects due to it being an old installation>Do i need two meters now? do i need to run a ground to each panel?They were 100 amp panels as well .