rswolff001
Member
I have an industrial panel.......supply 480vac, 500a MCCB......MCCB feeds into a distribution block... I'd like to have a 100a feeder from the distribution block go first to a contactor, then to a group of ganged (busbar) din-rail mounted circuit breakers. Is this allowable or does my feeder need to first go to a fuse or circuit breaker before the contactor? Distance from the distribution block to the contactor would be 2-3ft. From the contactor to the bus bar would be 1-2ft.
Can't seem to locate a reference to what I'm looking for in the code book.
Any help appreciated.
Thanks, Bob :dunce:
Can't seem to locate a reference to what I'm looking for in the code book.
Any help appreciated.
Thanks, Bob :dunce: