petersonra
Senior Member
- Location
- Northern illinois
- Occupation
- Semi-retired engineer
infinity said:If the engineer over designs a system, why should the installer care? If he's getting paid to do work beyond the scope of the NEC so be it. The only one that should really care is the guy who is paying the bill. He may be getting a lot more than actually necessary and paying for it too.
I don't design buildings, but every control system that I do design includes whatever I feel is necessary to support future needs without costing the end user an insane amount.
Contractors seem to be oriented towards cheap-as-possible, because that is often how they get the jobs in the first place, so it is understandable. Often they underbid and try to find some way around meeting the specs to lower their costs.
I usually specify minimum 3/4" conduit because I have seen what happens in the field when you pull wires through a 1/2" conduit for a few hundred feet. Just trying to get 4 wires pulled through it is a major effort.
Same reason I almost always spec minimum #12 to be pulled, even for control wiring that maybe on a 5A circuit. It is far more likely a #14 will be damaged in pulling than a #12.
Same thing with spares. I don't want to pay $5000 to run an extra wire that needs to be run down the road when for a few bucks it could have been put in when the original work was done.
I have been involved in projects where the change orders for the install exceeded the original amount the EC bid because the customer wanted the cheapest possible install. Often they bid it out themselves without any spec, sometimes even before drawings were available laying out what wires had to go where. Thats not an unusual situation and is why I usually put in a fair amount of capacity for things I don't even know about yet.
In fact, many customers have decided to forgo even having us come up with installation drawings, thinking the the few grand it might cost is a waste of money. They just give the schematics to the EC and say "wire it up". Often the EC's people cannot even read the schematics, which leads to "interesting" situations. I try not to laugh or tell them "I told you so", but it is hard.
The ECs laugh all the way to the bank.