.....When I teach wiring I have the following rules:
1) Work from the load back to the source. [makes it really hard to accidentally energize the circuit until it is all but completed.]
2) Connect all the grounding together wires first. ["They are the most important wires", and go to the back of the box.]
3) Connect the grounding wire to each device that needs one.
4) Connect the grounded wires next.
5) Connect the hot wires last.
This is what I follow as I have been thought this way by my teacher.
However, I voted "NO" in the pole and it only applies to smaller boxes with #12&14 conductors, however, if I have a 6x6 or larger splice box I always use a ground bar.