mshields
Senior Member
- Location
- Boston, MA
I've got a service comming from a pad mounted transformer. Main electrical room is just inside the building. So I'm running a duct bank from the pad mount to under the building. Once I'm under the building I no longer need the duct bank right. But I'm wondering how this transition is typically done? Do I continue my PVC conduits in the duct bank until I get to the steal sweep? Do end the concrete encasement precisely at the building line and continue on with direct buried PVC?
Mike
Mike