Attached sketch Panel CP location in your opinion has sufficient area for egress to and entrance from the panel CP working space in compliance with NEC 2017 section 110.26(c)(1) given its behind large gear?

I posted something similar but the question in this thread is different since in this thread question is about egress from and entrance to working space of Panel CP can be considered sufficient area or not its behind large gear

1122e389f5738c427f341d9e1fc604f1.jpg
 

tom baker

First Chief Moderator
Staff member
We have answered this. If you don’t like the panel location make a note on the plans “comply with 110.26”. Then it’s on the designer.
 