mshields
Senior Member
- Location
- Boston, MA
I've got an outdoor, flourescent sign for a building. Have reviewed Article 600 and it appears to me that I need a dedicated circuit for this. My client would like to tap off the nearest light pole. Going all the back to the facility is going to cost a lot of money (although we do own it on our drawings).
Is my interpretation that it must be a dedicated circuit correct. Paragragh 600.5 seems to be the operable one but it's not entirely explicit.
Thanks,
Mike