I'm in San Jose CA. I have a customer that has an existing overhead 200 Amp panel w breakers. He wants to add a second meter for an EV. Can I leave his existing service alone and install a second riser, meter, breaker next to main panel and have PGE splice wires together at weather heads?
How about a pull box located above panel and have new riser come into that first? Does anyone have a product number on pull boxes they have used in this situation?
Ideas and recommendations?
Thanks!