Knightryder12
Senior Member
- Location
- Clearwater, FL - USA
- Occupation
- Sr. Electrical Designer/Project Manager
We call out the new or existing AFC and AIC. We have never called out the SCCR.Interesting comments. Maybe someone could send me a DM to discuss the ratings in more detail. If the project is a renovation/addition, we do the field work on the existing equipment, but if it is new we size everything based on the calculations. I have not known anyone to call the utility for the rating. Another subject that has popped up on this thread is that I see AIC, SCCR, and AFC. We call out for the AIC on the drawings, does anyone call out for the SCCR? Again.. it may be best to send a private message or we can start a new thread.