We are back to this again with a new twist. We have 1 elevator Hostway/shaft and pit with 2 elevators side by side in it. Installed are 2 circuits 1 for lighting and one for the receptacles. This is installation is done per the engineers drawings. Today the state elevator inspector inspected and is requiring 2 circuits for lighting and 2 for receptacles, separated under each elevator that are in 1 common hoistway & pit. He is the AHJ so what can you do. The way I read the code is there are 2 circuits for the hoistway and the hoistway is the entire enclosed rated structure that houses the 2 elevators. The same issue is present at the top of the hoistway as in the pit.
Any thoughts?
Any thoughts?