dcadigan11
Member
We ran B-line solid strut channel with snap on covers. In the raceway is 277V lighting circuits, 2 separate circuits both #10 Thhn. The problem the inspector has is the one is from critical power and the other is normal power. Also there is a third life safety circuit that runs 10 lights, it is run in conduit separate from the normal & critical. The inspector wants all 3 circuits separated. Is there a code violation here with the normal & critical run together?