Atvkid4eva
New User
- Location
- Ohio
- Occupation
- Engineer
I am running some 1” EMT for a welding circuit. I am to the point where I need to pass through 7/16” plywood and then go up and into the bottom of my sub panel. I’m thinking that a LB body is best for this to pass through the wall and it will give me a spot to pull the wires. What would you guys recommend I do behind the wall? Flexible conduit of some sort? I would prefer to not remove the plywood if possible. Let me know what you guys would do to make this as clean as possible. Pics below for reference, I have not drilled the pass through hole yet. Thanks!