358.30 (A) EMT shall be securely fastened in place-------
I'm looking at a 4" emt hanging 20' down from the ceiling by the use of
3/8 allthread and minerallic clamps, the run is 200' long, if you get on a lift
and go to the pipe you can shake it 5' - 10' easy.
Is this a code compliant installation ?
I'm looking at a 4" emt hanging 20' down from the ceiling by the use of
3/8 allthread and minerallic clamps, the run is 200' long, if you get on a lift
and go to the pipe you can shake it 5' - 10' easy.
Is this a code compliant installation ?