frogneck77
Senior Member
- Location
- Shelton,CT
I am bidding a set of plans for an 11,000 square foot home.The scope of work says to" Provide properly sized panels for new electric service". No other specs on the service listed. I did a load calc based on all the info I have and came up with 289 Amps. I did not account for the elevator or future pool. Any suggestions on what to figure for future pool? I also remember reading somewhere that an electrical engineer is required to design any service over 400A. Is this true?