The firms I've been at always detail a duct bank with encased concrete for the service no matter the situation. The system I'm working on is 480V and has a 600A secondary service for an office building, and a 600A service for a PV system over the parking lot. I'm thinking of detailing (2) 3" Sch. 40 PVC to be buried with back fill (no concrete). Depths will be detailed per Table 300.5(A). The runs are ~100'. When would fiberglass conduit come into play?