RJH333
Member
- Location
- New Jersey
I have several ENT conduits stubed up from a concrete floor I installed a Manufactured bottomless metalic trough over the conduits and ran 2 -2" Emt conduits up from the top of the metal trough into the bottom of the panel. I ran the circuits through the trough and into the panel where i terminated the ground wire on a ground bar attached to the panel and ran the neutrals to the neutral bar and the circuits to their breakers. the inspector wants the grounds terminated at the trough with a lug for each wire or a terminal strip mounted to the trough. Is the trough allready grounded form the connection of the 2" emt ran down to the trough ? Where can I find this in the NEC?