Estimating by Task?

mooreaaryan

Member
Location
Bakersfield CA
Occupation
Electrician
I am estimating work by task. Trying to understand to account for wire pull section. Should I be using the length of the run times number of conductors to get the manhours or should it just be the length of the run regardless of the conductor count? The base unit I am using is NECA devalued but our historical information is not tight enough to be reliable due to use of temp workers and contractors on job. If you're a pro estimator I would love to get advice on best practice for estimating and job budgeting.
 