This is a 3 unit reno, with about 80% of the building re-wired. There is an old 400a service that was never grounded to the city water entering the building.
I required that to be done. Would other inspectors have done the same?
Thanks for any feedback.:smile:
 
This is a 3 unit reno, with about 80% of the building re-wired. There is an old 400a service that was never grounded to the city water entering the building.
I required that to be done. Would other inspectors have done the same?
Thanks for any feedback.:smile:

I should have said "bonded" to the h2o. :D
 