steveve1
Member
- Location
- Tucson, AZ
While 90% of our construction projects are engineered, we are more often than not asked to provide temporary power to the project without engineering oversight. Normaly we place this temporary service as close to the available power source as possible. In our area, fault currents can range to 75K amps at the available source. In providing temporary power to the project should the let-thru current derived from the fuse current limiting graph dictate the AIC rating of the downstream panel and breakers? eg. 42K available at line side of 100a JJN fuse, fuse chart puts let-thru current at approx. 7K. Is a 10K panel and breaker proper?