I have a new building and lift station that require power. Currently the building will get its power from a close by power pole. The lift station on the other hand i'm not sure which is the best way to feed it. Should i feed it directly from the power pole and provide with its own breaker/meter. Or should i feed it from the building service and tap off a bus and provide a seperate breaker by the lift station. See attached picture. Which way do you think is the best way to do this? also for the pathway of lift station. should i go under the building since it has not been built yet or around it? Life station electrical requirments not known yet. Thank you