Javi_M
Member
- Location
- San Antonio, Texas
Just hoping for some quick help understanding if a contractor actually specify correctly the electrical hardware for a job I require.
Rated Amperage: 500 A
Run Length: 200 Feet
Line Voltage: 480 Vac 3-Phase
Load: 360 FLA
Conductors: 2-per phase plus 1 ground
I'm looking to understand if this feeder requires a 2 EMT conduit runs and if a 4/0 wire gauge is adequate to carry the load or did they under rated the wire.
Regards,
Javi
Rated Amperage: 500 A
Run Length: 200 Feet
Line Voltage: 480 Vac 3-Phase
Load: 360 FLA
Conductors: 2-per phase plus 1 ground
I'm looking to understand if this feeder requires a 2 EMT conduit runs and if a 4/0 wire gauge is adequate to carry the load or did they under rated the wire.
Regards,
Javi
