Scenario.
24 sets 4#600.
500' of it underground with pull box & (5) 90's
60' inside the building with 4 90 degree bends.
Would you need/want to splice in the run?
I'd say no.
24 sets 4#600.
500' of it underground with pull box & (5) 90's
60' inside the building with 4 90 degree bends.
Would you need/want to splice in the run?