Ok, a few points to everyone's input. 1st, I attached the
entire drawing, redrawn from original per the below ideas from this discussion. I originally cropped the image just to make it easier to see the area of concern - my bad. So the total PV is 80A with 2 7600 inverters @ 125% output. As for
705.12 bus rules, options
a and b are not possible and assuming I don't swap the apartment and house as Jaggedben suggests (which is a very interesting idea btw but still limits me to 125A max) then that leaves option "c". And Wayne is correct, the feeder wires on the feeder lugs are getting relocated to the BU subpanel so it won't violate 705.12
taps rule, which only leaves the PV breaker and welder breaker on the 200A MSP lower bus. This is a great idea unless I'm forgetting something (highly possible)!
The welder's OCP is over what is needed and can be dropped to 25A easily if not more which would allow a 175A PV breaker in the MSP: 175 + 25 = 200A total bus rating for option "c". 175A is more than enough for the loads on the 200A subpanel in the house. It's a doublewide trailer btw at about 2K sf with standard electric appliances. Load calcs derated are less than 120A.
So am I missing something?