Larry hippich
New member
- Location
- Uniontown ohio
Good morning! I have a storage building that the architect had drawn to have 1000 A service with main breaker . Off of the thousand amps main service is a meter pack with 12 60 A panels. The drawing is showing each of the feeders to each panel to be three wires two hots and the neutral wire there is no equipment ground shown to separate the conduit used in this application is PVC wondering if anybody knows of any code article that would back this up without using a separate equipment ground.also all the main grounding is done at the main of the service off of their thousand amps breaker