gadfly56
Senior Member
- Location
- New Jersey
- Occupation
- Professional Engineer, Fire & Life Safety
Does anyone have any experience running an SLC between buildings? The manufacturer (Siemens) allows this. Tech support said I could only go underground, and pointed me to article 225 (2005 NEC), but that seems to be for power circuits, not power-limited communication circuits. In addition, they require that this portion of the SLC be shielded (it normally doesn't have to be), and the tech didn't seem to understand when I asked if RMC would be adequate for shielding.
I took a look at 760.11 which points me to 800 parts II, II, and IV or 300 part I. I'm having trouble visualizing the implementation of the various article requirements. Can anyone give me a list of materials, installation method/sequence, and a primer on how they meet the article requirements? From what I can tell, I probably will use article 800 but I just don't know. Thanks in advance for any help.
I took a look at 760.11 which points me to 800 parts II, II, and IV or 300 part I. I'm having trouble visualizing the implementation of the various article requirements. Can anyone give me a list of materials, installation method/sequence, and a primer on how they meet the article requirements? From what I can tell, I probably will use article 800 but I just don't know. Thanks in advance for any help.