safetyJoe
Member
- Location
- Hebron, Kentucky
We have a 100,000 sq ft warehouse that has two separate services. We installed a man door and a garage door into that demising wall. The electrical inspector is now telling me that to make that door code I have to install a 3/4 hour fire door. He said that this was referencing code 230.2 and 230.72. When I read those codes, I did not see anything about a fire rated demising wall. I have only taken the 30 OSHA course so I by all means do not know if I am not reading the whole code or if I am being played a bit. The building inspector approved the work 2 years ago, but sent us a letter that the electrical inspector told him that it is not correct due the NEC 2011 230.2 and 230.72. Any help would be appreciated.