mstrlucky74
Senior Member
- Location
- NJ
Anyone familiar with this in NYC? I know it's when the fire alarm system is down and you have men/man standing by in case of a fire. I thought there was another alternative to this.
Anyone familiar with this in NYC? I know it's when the fire alarm system is down and you have men/man standing by in case of a fire. I thought there was another alternative to this.
Anyone familiar with this in NYC? I know it's when the fire alarm system is down and you have men/man standing by in case of a fire. I thought there was another alternative to this.
Evacuation.![]()
Well OK, that works too. :roll: The customer may find this solution to be sub-optimal.hmy:
Anyone familiar with this in NYC? I know it's when the fire alarm system is down and you have men/man standing by in case of a fire. I thought there was another alternative to this.
It all depends on what is being done. This could also apply if you were doing cutting of steel or welding within an occupied building. I know that you have been posting a lot of questions geared towards building. in this case you may be required to get a hot work permit along with a fire watch that may include just a single fireman or maybe even an engine company.
I looking at 5 floor with each floor taking approx 3 days to complete. So I assume we need around th clock fire watch. I can't see the system being put back online after each shift as it's a complete floor demo.
There are usually ways around this. It would obviously depend on what the goal of the fire watch is and whether the AHJ is just concerned with fire protection or is trying to be punitive or difficult.
For example, if there is a sprinkler system then full coverage smoke detection can be "ignored" as the building has fire detection in place. If the building isn't occupied at night then Notification may not be needed. If it is needed, then with a little planning you can make sure the new is done and activated daily. It is rare that I have seen a situation where the fire alarm system can't be activated at the end of a shift.
In larger buildings and upgrades/renovations, the drawings and specs usually call for maintaining the existing level of fire protection throughout the project duration.
I meant the entire system which should be evident to you in the body of what I wrote. Throughout the work day the system is generally taken "off line" in regards to calling out to the Central Station, but still operational. I wasn't intending to do a 10 page dissertation.
Sorry, the comment was intended to convey the requirement to the OP. I've been around here long enough to know you know your stuff.
I'm sorry too, I must be touchy this morning.
Try to cheer up; it's Friday!Unless you have to work the weekend, in which case forget I mentioned it. :ashamed1:
