I have a job where the basement has passed the Rough-In stage and the Property Owner does not want to complete the basement at this time.
The Local Inspector is requiring the walls be covered, not finished, just covered to "protect from physical damage" where there are electrical wires. Most of the circuits are not connected in the panel, but in the panel.
As an Inspector would you require this as well?
PS.. I did not do the wiring for this. I have been asked to come in after another contractor to finish the job.

The Local Inspector is requiring the walls be covered, not finished, just covered to "protect from physical damage" where there are electrical wires. Most of the circuits are not connected in the panel, but in the panel.
As an Inspector would you require this as well?
PS.. I did not do the wiring for this. I have been asked to come in after another contractor to finish the job.