Do to one GC customer of mine taking too long to pay my invoices I now send a notice to the owner(s) of the property where the work is being performed. My notice informs the owner(s) that I have been hired by (name of GC) to supply material and perform work on the property of the owner(s). My notice also recommends that the owner(s) request lien waivers from me prior to dispersing payments to the GC.
I think the one problematic GC I do work for has figured out that I'm sending these notices but pursuant to the Mechanic's Lien law in Illinois I am required to send said notice.
If I fail to send the notice to the owner(s) within 60 days of substantial completion of the project I could have a hard time installing my lien against the property.
So far only two customers have requested said waivers.
I think the one problematic GC I do work for has figured out that I'm sending these notices but pursuant to the Mechanic's Lien law in Illinois I am required to send said notice.
If I fail to send the notice to the owner(s) within 60 days of substantial completion of the project I could have a hard time installing my lien against the property.
So far only two customers have requested said waivers.