GC wrote this is in...

Alwayslearningelec

Senior Member
Location
NJ
Occupation
Estimator
GC I'm bidding project to wrotew this in thier document and wants me to agree. I think it's BS. The engineer/PE should be responsible to show all required work. Thoughts?

1732115994461.png
 

Strathead

Senior Member
Location
Ocala, Florida, USA
Occupation
Electrician/Estimator/Project Manager/Superintendent
Like, I might be okay with 'minor detail that is necessary for a code compliant installation'. But this language could be used to put you on the hook if the AHJ and PE/designer disagree about what's code compliant on some major aspect. That's unacceptable.
I may also agree with accessory. That would be like aircraft cable for a fixture that are listed in the part number.
 

jap

Senior Member
Occupation
Electrician
That's a pretty common statement found on most job bids.
Just be sure to clarify your quote.

Jap>
 

Seven-Delta-FortyOne

Goin’ Down In Flames........
Location
Humboldt
Occupation
EC and GC
The specs, plans, and bid documents cannot, and will not, show every single locknut, wire connector, screw, junction box, strap, piece of uni-strut, etc.

Some sub-contractors will use that to try and CO the everlasting sunofagun out of a project, so there has to be some kind of verbiage that negates that.

It sad but factual that things that should be obvious like that, need to be spelled out, but that’s what happens when people refuse to live with honor, especially in their business.
 

Seven-Delta-FortyOne

Goin’ Down In Flames........
Location
Humboldt
Occupation
EC and GC
GCs rely on their specialty sub contractors to know more about their specific trade than they do, and that is what the RFI process is for. If the EC sees that something is a glaring code violation, or something is missed or unbuildable as drawn, he should submit an RFI for clarification, and now all the subs are on the same page.

It used to be standard practice for a contractor to pour over a set of plans looking for what was missed, then submit a low bid with the plan to make up the required profit on exorbitant COs once you have the customer over a barrel.

There was a large road building contractor that did a job in my area many years ago that was famous for that. They built a 12 mile highway bypass and made more on the COs than they did on the original contract.

Language like this is intended to curtail that behavior.
 

jim dungar

Moderator
Staff member
Location
Wisconsin
Occupation
PE (Retired) - Power Systems
GCs rely on their specialty sub contractors to know more about their specific trade than they do, and that is what the RFI process is for.
They also expect their subcontractors to know what local and current requirements might come into play. Nationally prepared plans/specs are used in many different communities without taking into account local codes or power company requirements. I have seen contractors order incorrect or unsuitable equipment and then try to use CO to get the proper stuff on site instead of using an RFI before the contract.
 

jaggedben

Senior Member
Location
Northern California
Occupation
Solar and Energy Storage Installer
I understand why they want it, but I would re-write it so that can only be construed to apply only to minor items that are implied by the drawings and within the scope contracted for.
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
I understand why they want it, but I would re-write it so that can only be construed to apply only to minor items that are implied by the drawings and within the scope contracted for.
I agree. Let's say there a fire pump on the 50th floor that they left off of the drawings and you don't have it in your estimate. Now they say " it's necessary for a complete and functional installation" and want you to eat the installation of 50 stories of 2 hour rated MC cable.
 

mtnelect

HVAC & Electrical Contractor
Location
Southern California
Occupation
Contractor, C10 & C20 - Semi Retired
In my early days of starting out in the world of contracting ... I bid a job for a small shopping center. The bid documents stated not to include the lighting because the tenants have not been selected yet. So, our bid was selected. Before we signed, the developer asks if our bid included the lighting. We said no, because the documents stated not to include the lighting.

That was my first inclination that the bidding process was flawed.

After several more run ins with developers and taking a General Contractor to court on a Mechanics Lein (which took me five years to settle) I changed to being a HVAC service contractor. Best move I ever made !
 

mtnelect

HVAC & Electrical Contractor
Location
Southern California
Occupation
Contractor, C10 & C20 - Semi Retired
I remember a game show called "Can You Name That Tune" ... You had to name that tune within three notes. Contracting is similar to that show.
To win a "Bid" you have to be the "Low Bidder" ... Congratulations you are the low "Bidder" ... What did I leave out ?
 

mtnelect

HVAC & Electrical Contractor
Location
Southern California
Occupation
Contractor, C10 & C20 - Semi Retired
Then comes the best part ... the general asks you if you could do some work that he forgot about. If you will do it for free ... I will compensate you on the next job.
 
Top