Try to explain my service. I have 400 amp main disconnect feeding 4 100 amp meters that have 4 100 amp breaker enclosures off them which in turn feed 4 panels with service cable downstream. This whole service starts from top to bottom Main disconnect to trough and so on and it is all in EMT except for the service cable obviously. So here is my question do I have to run a GEC through the whole system?including the meter pan (5 terminal) or is the equipment sufficient?
Should everything after the main disconnect be treated as a sub panel?
Should everything after the main disconnect be treated as a sub panel?
Last edited: