I was at a new sewage uplift station and was going to wire the back up generator in and found the following, when installing the base pad the instructions called for two conduites one for power one for signal, when reading the instructions the signal conduit containd 7 wires, 2 wires for 240v sensor, 2 12 volt dc sensors wires, and 120 v for a battery charger hot, netural and ground, the generator main power is 480/277 3 phase,
My question is I know the nec does not all different voltages in the same conduit, but in the signal conduit is showing to install 3 different voltages in it? Is there a nec acception to this rule or was this a engeneer mess up?