I have a customer/ Urgent care clinc that would like me to bid on installing a back up generator. the building is 10 years old. and the clinc is already up and running for 10 years. The clinic is not required to have a back up nor any crtical care circuits.
the reason for the generator is due to the local utily Excel Energy not keeping up on there equipment and every once in a while will drop a phase or 2 and the clinic loses lights and computers.
I have never bid on a generator so my question is would I need a Engineer to draw up the plans or would the generator supplier draw up plans.
which generator manufactours would you recomend. the building power is 480V 3 phase. lighting is 277V.
the reason for the generator is due to the local utily Excel Energy not keeping up on there equipment and every once in a while will drop a phase or 2 and the clinic loses lights and computers.