Shujinko
Senior Member
When performing the annual load bank test on a generator as required by NFPA 110, I wanted to know the following.
1. Can the normal power to the building be maintained operational while the load bank test takes place?
2. If so, can the ATS be set to stay in the normal position and not transfer to the to emergency position during the test? How is this done?
3. In my case, I am designing a generator project that will have one load breaker and one breaker for connecting the load bank mounted on the generator. Do I have to interlock these breakers to make sure that when the load bank breaker is in the on position, the load breaker is in the off position? Code requirement?
1. Can the normal power to the building be maintained operational while the load bank test takes place?
2. If so, can the ATS be set to stay in the normal position and not transfer to the to emergency position during the test? How is this done?
3. In my case, I am designing a generator project that will have one load breaker and one breaker for connecting the load bank mounted on the generator. Do I have to interlock these breakers to make sure that when the load bank breaker is in the on position, the load breaker is in the off position? Code requirement?