I have an existing residence where I will be installing a new 200A enclosed main breaker between the service meter load side conductors and the existing 200A main panel. Here's how I understand it... The supplied screw that bonds the Neutral lug assembly to the enclosure is the "main bonding jumper" and the GEC's (relocated from existing main panel) and EGC's (including the EGC from the SER now feeding the main panel) are landed in the factory supplied ground lugs in the new enclosure. As I write this, I think I've convinced myself, but will still throw it out there for confirmation.