Re: graphic eye
Eric,
I ahve installed 2 of these systems. I sleeved the LV cable with 3M heat shrink to give myself some piece of mind, good electrical tape will work as well.
Lutron has an app note on this that addresses the issue:
Click here
Their tech support number is also VERY good, they have answered the weirdest questions to me without any problems.
I don't think you need to sleeve it, but what does 10" of heat shrink cost? Also, if 120 ever got on the Class 2 conductors, you'd fry all of your accessory controls, and I'm sure you know that those aren't cheap.
Oh yeah, you said that you are using boxes w/ plaster rings...I'm not sure these are deep enough, I used masonry boxes (like a bowers MB-4), they are 3.5" deep and give you a lot more room than a 5g switch box with a 4 gang cover, I think thats only 2" deep, check your lutron manual, as this may be too shallow. They can take LV partitions as well, if you need them.
Mike