alaskanassassin
Member
- Location
- Fairbanks, Alaska
I started wiring a house for a friend and before I got there they had a 200 amp single phase service already put up on a pole. The house is 250 feet away. They purchased three 3/0 direct burial cables and proceeded to bury it with no ground. I am considering digging a new trench and running a #6 ground between the house and pole, is this the correct thing to do? Thanks