A pump manufacturer wants a ground for grounding the power supplies for pumps they are testing.
Properly it should be a bar bonded to the service ground at the service?
Properly, any fault should have a low impedance path back to the service which should contain the sole connection/bond between the grounded conductor from the utility anything that requires Equipment Grounding.