hurk27
Senior Member
- Location
- Portage, Indiana NEC: 2008
And I have never seen a meter that has a lug for a GEC.
Our state rules do not allow bonding GEC in meter socket.
As Don points out the NEC allows the connection between the service drop and service equipment enclosure. Its most commonly done in the service enclosure as thats the easiest location to make the connection.
The AHJ would likely wonder whats up if it was done at the service drop. This violates the "don't confuse the inspector" rule.
Now you have, Note the extra lug to the right of the neutral terminals between the red insulators.
Indiana also allows the GEC to land in the meter base as some inspectors also tried to say it wasnt acessable for inspection, but it was shown that it always is before the meter is sealed at the time of the service inspection.
We get power to the service while the house is still under construction for temp power.