I have a question regarding service disconnecting means, grounded conductor, grounding conductor, and bonding.
An industrial facility (480Y/277) we are installing consists of a 2000A MCB at the utility poles... the feed goes about 50ft into an 2000A MCC building with a 2000A MCB at the entrance (which is also rated for service disconnect although not used for such). We have a 480/277v lighting panel inside that we were planning on using for lighting (at 277), other than that all the loads are line to line. The problem is that there is only one bar inside MCC for grounding so IMO we would bond there and run one grounded conductor along with the other three wires back to the service disconnecting means and up the pole. Also at this point the engineer for the company we bought this equipment from said this MCC was not designed for 4wire and that the 480/277 lighting panel was installed by mistake. So now I am wondering if bonding in the MCC would be wrong and to completely scrap any thoughts of line to neutral loads, also the MCC is not the service disconnecting means if that matters.
Do you guys have some ideas? Thanks
An industrial facility (480Y/277) we are installing consists of a 2000A MCB at the utility poles... the feed goes about 50ft into an 2000A MCC building with a 2000A MCB at the entrance (which is also rated for service disconnect although not used for such). We have a 480/277v lighting panel inside that we were planning on using for lighting (at 277), other than that all the loads are line to line. The problem is that there is only one bar inside MCC for grounding so IMO we would bond there and run one grounded conductor along with the other three wires back to the service disconnecting means and up the pole. Also at this point the engineer for the company we bought this equipment from said this MCC was not designed for 4wire and that the 480/277 lighting panel was installed by mistake. So now I am wondering if bonding in the MCC would be wrong and to completely scrap any thoughts of line to neutral loads, also the MCC is not the service disconnecting means if that matters.
Do you guys have some ideas? Thanks