bjb
Member
- Location
- Union, MO Franklin County
On a 480 volt 3 phase 3 wire service. I need to ground the center leg at the CT cabinet. My question is does that ground need to be sized according to 250.66 or 250.122. If anyone can provide me with the correct code ref as for as the correct way to bond and ground this particular service i would appreciate it. Thanks