S screwybazooie Guest Sep 25, 2005 #1 a second building supplied by a grounded system requires a separate bonding jumper or grounding electrode
a second building supplied by a grounded system requires a separate bonding jumper or grounding electrode
dereckbc Moderator Staff member Location Plano, TX Sep 25, 2005 #2 Re: grounded system I am sorry is this a question? It can be done two ways, with and without a bonding jumper at the sepearate buildings. Depends if there is any metalic paths between the two. 250.32 covers the two options.
Re: grounded system I am sorry is this a question? It can be done two ways, with and without a bonding jumper at the sepearate buildings. Depends if there is any metalic paths between the two. 250.32 covers the two options.
roger Moderator Staff member Location Fl Occupation Retired Electrician Sep 25, 2005 #4 Re: grounded system Read 250.32 as Dereck points you to. Roger