DIYBamaGuy
New User
- Location
- Alabama
- Occupation
- Retired Engineer
My situation. Power Company requires that the ground rod terminate outside in the meter socket. I have a back to back Main service breaker panel inside connected to the meter base by ridged conduit. I have ran 3 wires, 2 hot and neutral, from meter socket to Main breaker panel. The panel I am using is a Square D Homeline Snap on Neutral panel. It does not have separate ground and neutrail bus bars installed. So my questions are:
1. Is my Main service breaker panel considered a service disconnect or a sub panel?
2. If it is a Service Disconnect,
a) is it ok to terminate my circuit grounds and neutrals on the same bus bars In that panel even though the ground rod is terminated at the meter socket?
b) do I install the green bonding screw?
3. If it is a sub panel,
a) I assume I need to add separate ground bus bars in the Main service breaker panel, correct?
b) I would also think I would need to run a separate ground wire between the meter and panel but there is no place to terminate it inside the meter socket. Is this correct thinking and suggestions on terminating it in Meter socket?
c). No green bonding screw, correct.
Thanks for any help and suggestions provided.
1. Is my Main service breaker panel considered a service disconnect or a sub panel?
2. If it is a Service Disconnect,
a) is it ok to terminate my circuit grounds and neutrals on the same bus bars In that panel even though the ground rod is terminated at the meter socket?
b) do I install the green bonding screw?
3. If it is a sub panel,
a) I assume I need to add separate ground bus bars in the Main service breaker panel, correct?
b) I would also think I would need to run a separate ground wire between the meter and panel but there is no place to terminate it inside the meter socket. Is this correct thinking and suggestions on terminating it in Meter socket?
c). No green bonding screw, correct.
Thanks for any help and suggestions provided.