patrick@michael-clarke.co
Member
If we add a Service Entrance rated transfer switch in front of the current MDP (first point), is it permissible to remove the bond at the ATS and leave the bonding in the existing MDP?
So we would have the load side of the meter going to the ATS, meter grd to ufer. Equipment grounds between ATS and MDP and ATS and generator. Load Side of ATS to MDP.
Acceptable? Historically, we have treated the MDP as a sub after installing the ATS, but I sure would like to avoid separating the G&N in the MDP.
Pat...
So we would have the load side of the meter going to the ATS, meter grd to ufer. Equipment grounds between ATS and MDP and ATS and generator. Load Side of ATS to MDP.
Acceptable? Historically, we have treated the MDP as a sub after installing the ATS, but I sure would like to avoid separating the G&N in the MDP.