Grounding Delta windings

Status
Not open for further replies.

Ohmy2

New member
We have a temporary service being installed at a very large industrial plant in California. Within this site there is a service building with a 480V-120/208V Delta Wye system providing power to the building equipment. The temporary service is a 12kV-120/208V Delta Wye system with a temporary Switchgear and off this switchgear the electricians are installing a 120/208V-480V Wye Delta booster transformer with the primary circuit from the temporary switchgear protected with a circuit at the switchgear and a fused disconnect switch on the secondary winding which will supply the previously mention service building, with the 480V-120/208V transformer. My question is when the 3-phase delta system is routed to the 480V Delta winding at the building are we required to ground one corner of the delta winding. The code book seems a little vague about using non-grounded systems.
 
You are not required to ground a delta configuration; however, there are rules that must be followed such as ground detector lights. :)
 
Ohmy2 said:
We have a temporary service being installed at a very large industrial plant in California. Within this site there is a service building with a 480V-120/208V Delta Wye system providing power to the building equipment. The temporary service is a 12kV-120/208V Delta Wye system with a temporary Switchgear and off this switchgear the electricians are installing a 120/208V-480V Wye Delta booster transformer with the primary circuit from the temporary switchgear protected with a circuit at the switchgear and a fused disconnect switch on the secondary winding which will supply the previously mention service building, with the 480V-120/208V transformer. My question is when the 3-phase delta system is routed to the 480V Delta winding at the building are we required to ground one corner of the delta winding. The code book seems a little vague about using non-grounded systems.
No you are not "Required" by the NEC to corner ground the "B" phase. But like Charlie mentioned there are requirements to be followed.
 
Status
Not open for further replies.
Top