For those who have done Cellular equipment installs. A Master ground bar is installed where a halo ground ring bonds all the equipment together with antennas and metal platform. The drawings requires a master ground bar so everything is terminated at one location. The platform is a floating platform on top of roof and the only ground on equipement will be the one insite the electrical panel. Normally on other projects i have seen that a ground rod or building steel with a EGC/stinger going straight to master ground bar. Is there a requirement in NEC or a lightning issue with Master ground bar? or some other standard i can look up for this type of application.