Me again. I have a customer who is adding a large out-building. He has a 200a service on the house, meter outside, main-breaker panel inside, which supplies two electric-heat HVAC systems, meaning there's little headroom, amperage-capacity speaking.
Instead of adding a 100-amp breaker to the already-full panel by using tandems, if we upgrade the service, and place a disconnect for the new underground feeder next to the meter, must we also add a disconnect for the existing panel for the purpose of grouping, or is labeling adequate?