Hey guys I did an old house and passed the house but the service outside I failed. It is an overhead service. The only thing I can think is that I didn't ground the 2inch rigid that goes up. I've only done a handful of overheads and I vaguely remember the process.
Do I just run a #6 THHN green from the bottom of the 2 inch rigid (just above where it screws into my panel. Then run the ground around and into a romex connector on the bottom and land it on my ground bar? I can't remember how I kept the wire clean running around the panel... If that's even the problem.
heres what the report says:
Inspection Report
Residential Electrical
332 - Change of Service
Correction Required
This meter base is approved where it sat except for the requirement of a multi utility
ground bar which has not been installed
Do I just run a #6 THHN green from the bottom of the 2 inch rigid (just above where it screws into my panel. Then run the ground around and into a romex connector on the bottom and land it on my ground bar? I can't remember how I kept the wire clean running around the panel... If that's even the problem.
heres what the report says:
Inspection Report
Residential Electrical
332 - Change of Service
Correction Required
This meter base is approved where it sat except for the requirement of a multi utility
ground bar which has not been installed